Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
(KEY DECISION)
Report No. 140/2017 from the Chief Executive was received.
Mrs Briggs – Chief Executive, introduced the report, the purpose of which was to update Cabinet on the progress made to date on the Digital Rutland project; to make a recommendation for Phase 3 to maximise the fibre deployment and superfast broadband coverage; and to consider a request for revenue funding for the associated project management, consultancy and legal support.
During discussion the following points were raised:
ix. Phases 1 and 2 of the Digital Rutland Project had been a success, providing fibre into hard to reach areas that other Local Authorities were still to tackle. The Council had not publicised this success story as the subject can be complex and improvement cannot be made outside the intervention area. An extensive press campaign was planned if phase 3 of the project was approved.
DECISION
1. Cabinet NOTED the update on Digital Rutland.
2. Cabinet APPROVED the capital funding requirement as outlined in Exempt Appendix B, Option C to Report No. 140/2017 to enable a further phase of deployment of superfast broadband coverage.
3. Cabinet APPROVED £25k of additional revenue budget to cover project management, consultancy and legal support to implement and monitor delivery.
4. Cabinet DELEGATED AUTHORITY to the Chief Executive in consultation with the Portfolio Holder to sign a Change Form to the existing contract to effect the further investment, subject to full project assurance, state aid approval and value for money assessments.
Reasons for Decision
1. The recommendations would provide the maximum coverage of superfast broadband in the Digital Rutland project intervention area.
2. To support the delivery of: the Council’s strategic aims and objectives; the Council’s Corporate plan; and Rutland’s Economic Growth Strategy.
3. To support inclusive economic and well-being objectives.
4. To support more effective delivery of public services.
5. To exceed BDUK UK Superfast Broadband coverage objectives of 95%.
6. To enable the accelerated gainshare offer by BT to be taken up and to utilise pre-approved residual capital funding.
Publication date: 18/08/2017
Date of decision: 15/08/2017
Decided at meeting: 15/08/2017 - Cabinet
Effective from: 23/08/2017