Casepak and New Earth Solutions t/a mid UK- exercise of the option to extend the existing contracts for a further 12 months from 1st April 2021

Decision Maker: Strategic Director for Places

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To exercise the option to extend both contracts for a further 12 months from 1st April 2021.

To continue to enjoy services in relation to the treatment of dry mixed recyclables and green waste respectively pending retender in due course.

Decision:

Both contracts will be extended for a further 12 months. The arrangement with mid uk is that the contract price is fixed and there will be no increase during the extension period. With casepak possible changes to the price mechanism wef 1st April 2020 remain in negotiation and which will potentially flow through into the extension period in due course..

Alternative options considered:

Do not exercise the option

Publication date: 20/10/2020

Date of decision: 16/10/2020