Report No. 76/2018 was received from the Director for Places (Environment, Planning & Transport). The purpose of the report was to present the findings of the highways Maintenance Contract 2016/17 audit and to inform Members of the actions taken in response to this.
RESOLVED
- The Committee NOTED the Highways Maintenance Contract 2016/17 report and the actions taken by Officers to address issues raised.
- The Committee AGREED that a further update on any outstanding issues would be provided in June 2018.