ITCP-2019-42 – Barleythorpe Road/Burley Park Way roundabout

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To provide a formal pedestrian crossing at the Barleythorpe roundabout. Scheme was identified as required as part of the 2009 Hawksmead application and was included within the S106 agreement.

The scheme had not progressed due to the S106 agreement becoming void through the 2011 Hawksmead application. The scheme has since been identified as required through a highway assessment and requests by the parish council for school children safety.

Cabinet AGREED that authority be delegated to the Chief Executive and relevant Portfolio Holder to add small schemes (less than £50k) to the capital programme on the condition that all decisions are reported in the Quarterly Finance Report (Report No. 191/2016, Appendix A, para 2.4.4).

Decision:

To provide a formal pedestrian crossing at the Barleythorpe roundabout.

Alternative options considered:

Option 1 - To provide a formal pedestrian crossing at the Barleythorpe roundabout. Scheme was identified as required as part of the 2009 Hawksmead application and was included within the S106 agreement.

Option 2 - Not to provide the crossing

Publication date: 16/12/2021

Date of decision: 24/09/2021